Knauf
Rock mineral wool insulation, glass veil faced

Other manufacturers with similar products

unverified-manufacturerManufacturer page.

EPD: Rock mineral wool insulation, glass veil faced, 0.037 W/mK, 2.70 m2K/W, 100 mm, 40 kg/m3, Thermo-teK BD 040 WBS/ VBS/ VWS, Sound-teK BD 804 WBS/ VBS/ VWS/ WBD/ VBD/ VWD, Knauf

Manufacturer:
Knauf
Group:
Country of production:
HR country flagCroatia
Product name:
Rock mineral wool insulation, glass veil faced
Commercial names:
Thermo-teK BD 040 WBS/ VBS/ VWS, Sound-teK BD 804 WBS/ VBS/ VWS/ WBD/ VBD/ VWD
Category:
Insulation
Class:
Stone wool insulation
Type:
Stone wool unfaced

Environmental impacts

Global Warming Potential (A1-A3):
5.020 kg CO2e/m²
Technical specification:
0.037 W/mK, 2.70 m²K/W, 100 mm, 40 kg/m³
Available units for calculation:
m², kg, ton, m³
Unique identifier (OCLID):
687bf12f6108c625a43f2554

Sustainability data background information

EPD number:
EPD-IES-0020126:002
EPD program:
International EPD System
Publication year:
2025
Product Category Rules (PCR):
PCR 2019:14 Construction Products, version 1.3.3
Environmental standard:
EN15804+A2
Data source:
EPD Thermo-teK BD 040 WBS/ VBS/ VWS, Sound-teK BD 804 WBS/ VBS/ VWS/ WBD/ VBD/ VWD
Verification status:
Third-party verified (as per ISO 14025)
Upstream database:
GaBi